D-Star Progress/Update – 15 April 2008

VK6RWN: Brief Status Update

  • Power on
  • Feedline installed
  • Lightning arrestors ready
  • Racks installed
  • DSL installed
  • Server awaiting final config changes
  • UPS awaiting batts
  • PSU ready
  • 2m Filters being tuned
  • 70cm Filters being tuned
  • Antennas TBA (awaiting further discussions amongst all DSTAR groups)
  • WIA license waiting

In terms of physical work required, I believe that most of it could be knocked over in a weekend with a few helping hands. Perhaps if we can have some more people volunteering for some tasks, we can speed things along. food for thought.

73’s

Heath
VK3TWO/6